Flooring done in The Fishing Lodge in Rutland is part of the Rutland Water Nature Reserve.

A total of three areas were completed. The first area; the ladies and gents toilet blocks; a180m2 of existing marble floor was replaced with our 4mm Acrylicon Décor and coving system. The second area; the toilet entrance; an area of 24m2 of existing floor was replaced by our Acrylicon Décor Plus Non-Slip System and a coat of Safety Yellow Lacquer on the edge of the step. The third area; the gutting, warden and classrooms, an area of 42m2 the existing floor was replaced by our 4mm Décor System.

This work was completed over an eight day period.

Date Started: 14/03/05