WM Morrsons Supermartkets - Leeds Merrion Centre

Wm. Morrisons required a refurbishment to the floor in the busy store in the heart of Leeds City centre. We had to lay the floor with the minimum of disruption and ideally keep the store trading during normal opening hours.

Acrylicon Granito Flake System was specified, due to its attractive yet robust finish, and the colour blend was matched to Morrison’s corporate Terrazzo.

The customer floor area was over 3000m.sq. With Acrylicon Decor laid behind the deli and fish counters.

We had just 6 hours each night, yet managed to hand over a new section of floor each morning. Fitting into a tightly woven schedule meant we often had to work with other trades and staff nearby.

The project was completed in November 2007.